Construction activities continue at the Sgt. Pinney Memorial Pool project in Ridgecrest.
This week, crews completed concrete footing placements for the Community Building and continued underground utility installation serving the pool facilities. Site grading and subgrade preparation also progressed within the Competition Pool area as work advances across multiple portions of the project.
Upcoming activities include masonry work at the Community Building and continued underground utility testing and inspections.
AMG & Associates is proud to partner with the City of Ridgecrest on this important community recreation facility. The project will provide modern aquatic amenities designed to serve residents for years to come.