Construction is progressing at Mendota Elementary School as work continues on campus systems and outdoor areas. This week’s progress focused on wiring for the public address system, grading, and asphalt repairs. Together, these improvements are helping prepare the campus for everyday school use.
- Public address system: Crews pulled low-voltage wire and continued connecting the wiring needed for the campus PA system.
- Site preparation: Fine grading continued, and excess soil and debris were removed from work areas.
- Paved areas: Crews patched asphalt and placed base material in additional areas being prepared for patching.
The latest work brings both the campus infrastructure and surrounding grounds closer to completion. Once finished, these improvements will support a functional, welcoming environment for Mendota students and staff. We look forward to sharing more progress as work continues.